The project timeline depends on the scope of work. We establish a more detailed schedule once the project requirements and selections are defined.
A remove-and-replace keeps the basic footprint of the room intact, with appliances, plumbing, and utilities generally staying in their existing locations while old materials and finishes are replaced. A complete remodel involves more significant changes, such as reworking the layout, moving or removing walls, relocating plumbing or electrical, or moving appliances and fixtures.
It’s also important to remember that your remodeling timeline begins well before demolition. From the first Site Walk through final cleaning, there are three main phases:
1) Planning Process: Approximately 6–10 weeks
From our first visit through design development, material selections, pricing, and completion of the final planning package.
2) Material Purchasing & Trade Scheduling: Approximately 2–4 weeks
We order materials, coordinate deliveries, and schedule the trade partners needed for your project. Some products may require additional lead time before construction can begin.
3) Construction: Demo through Final Cleaning
Kitchen Remove-and-Replace: 10–14 weeks
Kitchen Complete Remodel: 12–20 weeks
Primary Bathroom Remove-and-Replace: 8–10 weeks
Primary Bathroom Complete Remodel: 12–16 weeks
These are estimates, not guarantees. Project complexity, material lead times, inspections, unforeseen conditions, and changes made along the way can all affect the schedule. But these ranges should give you a realistic starting point for understanding the time commitment involved.